Contact Tom Silk at (02) 9218 3200 to discuss your next project or query.
Corpus Christi Catholic High School
Oak Flats, NSW
Catholic Education Office
$4,700,000
Stage 1 of a new high school: Construction of 2 level classroom and administration building.
In spite of wet weather during the entire duration of the project, the building was delivered within the 36 weeks tight programme, in January 2006. The project was completed on time, on budget and as per the documents.